Daily Road Report, August 16, 2019

For immediate release: August 15, 2019 - 3:00pm
TC19-623

 

*This report includes road restrictions on Priority 1 (high traffic, high speed) streets only.
 
NEW
 
1ST AVE S SB LANES CLOSED FROM 21ST ST E TO 20TH ST E
(Craning material)
Start: August 16, 4:00 a.m. End: August 16, 12:00 p.m.
 
20TH ST W EB CURB LANE CLOSED FROM AVE C S TO AVE B S
(Sewer replacement)
Start: August 16, 8:00 a.m. End: August 17, 5:00 p.m.
 
MARQUIS DR E EB & WB LEFT TURN LANES CLOSED AT SIEMENS AVE
(Concrete repairs)
Start: August 16, 9:00 a.m. End: August 16, 3:00 p.m.
 
MARQUIS DR E EB & WB LEFT TURN LANES CLOSED AT ARTHUR ROSE AVE
(Concrete repair)
Start: August 16, 9:00 a.m. End: August 16, 3:00 p.m.
 
ONGOING
 
LENORE DR EB CURB & CENTER LANES CLOSED FROM CREE CRES TO PRIMROSE DR
(Concrete repairs)
Start: August 6, 7:00 a.m. End: August 16, 5:30 p.m.
 
TAYLOR ST E WB PARKING LANE & SIDEWALK FROM CUMBERLAND AVE S TO MCKINNON AVE S
(Concrete repairs)
Start: August 12, 7:00 a.m. End: August 19, 5:00 p.m.
 
PRESTON AVE S NB PARKING LANE CLOSED FROM TAYLOR ST E TO 8TH ST E
(Concrete replacement)
Start: August 6, 9:00 a.m. End: August 20, 5:00 p.m.
 
CUMBERLAND AVE S INTERSECTION CLOSED AT 14TH ST E
(Water main rehabilitation)
Start: July 8, 7:00 a.m. End: August 23, 5:00 p.m.
 
7TH AVE N ROAD CLOSED FROM QUEEN ST TO WARBURTON ST
(Water main replacement)
Start: July 2, 7:00 a.m. End: September 2, 5:00 p.m.
 
WANUSKEWIN RD NB LANES CLOSED AT 71ST ST E
(Road construction)
2-way traffic maintained in SB lanes
Start: August 6, 9:00 a.m. End: October 6, 4:00 p.m.
 
SID BUCKWOLD BRIDGE NB & SB LANES RESTRICTED
(Bridge upgrades)
Lanes restricted in both directions; NB lanes zipper merge near 8th St. SB single lane starting at 20th St.
Start: April 14, 8:30 a.m. End: October 31, 5:00 p.m.

MCORMOND DR INTERSECTION CLOSED AT BRIGHTON CMN
(Construction)
Start: July 25, 7:00 a.m. End: October 31, 5:00 p.m.
 
COLLEGE DR WB SPEED REDUCTION FROM MCORMOND DR TO MCKERCHER DR
(Construction)
Start: July 5, 9:00 a.m. End: November 30, 5:00 p.m.
 
AVE H S INTERSECTION CLOSED AT 11TH ST W
(Construction)
Start: March 11, 7:00 a.m. End: August 31, 5:00 p.m.
 
All restrictions will be lifted as indicated, weather permitting and barring any unforeseen circumstances.
Slow down, pay attention and respect work zones. Watch for pedestrians and work crews, and for everyone’s safety, please obey all detours, signs and barriers.