You are here

Daily Road Report, August 21, 2019

For immediate release: August 20, 2019 - 3:00pm
TC19-632

*This report includes road restrictions on Priority 1 (high traffic, high speed) streets only.
 
NEW
 
22ND ST E EB CURB & NEXT LANES CLOSED FROM PACIFIC AVE TO 1ST AVE S
(Crane lift)
Start: August 21, 5:00 a.m. End: August 21, 8:00 a.m.
 
PRESTON AVE S NB & SB DRIVING LANES CLOSED FROM JARVIS DR TO EAST DRIVE
(Sewer lining)
Traffic will be maintained in the parking lanes.
Start: August 21, 7:00 a.m. End: August 21, 5:00 p.m.
 
MCORMOND DR SB LANES CLOSED FROM NELSON RD TO ATTRIDGE DR
(Microsurfacing)
Start: August 21, 7:00 a.m. End: August 22, 7:00 a.m.
 
LENORE DR EB & WB MEDIAN & NEXT LANES CLOSED FROM WARMAN RD TO PRIMROSE DR
(Roadway resurfacing)
Start: August 21, 7:00 a.m. End: August 23, 4:00 p.m.
 
HIGHWAY 5 WB ROAD CLOSED FROM RANGE ROAD 3043 TO HIGHWAY 41
(Resurfacing)
Two-way traffic maintained in WB lanes.
Temporary traffic lights in place allowing 1-way traffic only
Start: August 21, 7:00 a.m. End: August 23, 6:00 p.m.
 
IDYLWYLD DR S NB & SB MEDIAN LANES CLOSED FROM SASKATCHEWAN CRES TO 8TH ST E
(Surveying)
Start: August 21, 9:00 a.m. End: August 21, 11:00 a.m.
 
CENTRAL AVE NB & SB MEDIAN LANES CLOSED FROM 109TH ST W TO 111TH ST W
(Line flushing)
Start: August 21, 9:00 a.m. End: August 21, 2:00 p.m.
 
8TH ST E VARIOUS LANE CLOSURES FROM WALPOLE AVE TO CAMPBELL AVE
(Borehole monitoring)
Start: August 21, 9:00 a.m. End: August 21, 3:00 p.m.
 
CENTRAL AVE NB & SB MEDIAN LANES CLOSED AT 115TH ST W
(Sewer lining)
Start: August 21, 9:00 a.m. End: August 21, 4:00 p.m.
 
TAYLOR ST E ROAD CLOSED FROM CAIRNS AVE TO MUNROE AVE S
(Manhole repairs)
Start: August 21, 9:00 a.m. End: August 21, 5:00 p.m.

3RD AVE N SB LANES CLOSED FROM 24TH ST E TO 23RD ST E
(Resurfacing)
2-way traffic maintained in NB lanes
Start: August 20, 11:00 a.m. End: August 23, 7:00 a.m.
 
OVERNIGHT
 
CLARENCE AVE S NB & SB MEDIAN LANES CLOSED AT CIRCLE DR S
(Deck sealing)
Start: August 20, 8:00 p.m. End: August 21, 6:00 a.m.
 
COLLEGE DR EB & WB MEDIAN LANES CLOSED FROM SASKATCHEWAN CRES E TO SPADINA CRES E
(Bridge Sealing)
Start: August 20, 8:00 p.m. End: August 21, 6:00 a.m.

ONGOING
 
MCORMOND DR NB CLOSED FROM STENSRUD RD TO ATTRIDGE DR
(Microsurfacing)
2-way traffic maintained in SB lanes
Start: August 20, 7:00 a.m. End: August 21, 7:00 a.m.

CONFEDERATION DR SB LANES CLOSED FROM LAURIER DR TO 22ND ST W
 (Resurfacing)
 Start: August 19, 9:00 a.m. End: August 21, 5:00 p.m.
 
MARQUIS DR W WB MEDIAN & NEXT LANE CLOSED & EB MEDIAN LANE CLOSED FROM IDYLWYLD DR N TO THATCHER AVE
(Water & sewer work)
Start: August 19, 9:00 a.m. End: August 22, 5:00 p.m.
 
TAYLOR ST E WB CLOSED FROM JACKSON AVE TO CUMBERLAND AVE S
(Resurfacing)
2-way traffic maintained in EB lanes
Start: August 20, 9:00 a.m. End: August 23, 7:00 a.m.
 
33RD ST W EB PARKING & CURB LANE CLOSED FROM CONFEDERATION DR TO JUNOR AVE
(Concrete repairs)
Start: August 20, 7:00 a.m. End: August 30, 5:00 p.m.
 
7TH AVE N ROAD CLOSED FROM QUEEN ST TO WARBURTON ST
(Water main replacement)
Start: July 2, 7:00 a.m. End: September 2, 5:00 p.m.
 
WANUSKEWIN RD NB LANES CLOSED AT 71ST ST E 
(Road construction)  
2-way traffic maintained in SB lanes 
Start: August 6, 9:00 a.m. End: October 6, 4:00 p.m.
 
SID BUCKWOLD BRIDGE NB & SB LANES RESTRICTED 
(Bridge upgrades) 
Lanes restricted in both directions; NB lanes zipper merge near 8th St. SB single lane starting at 20th St. 
Start: April 14, 8:30 a.m. End: October 31, 5:00 p.m.

MCORMOND DR INTERSECTION CLOSED AT BRIGHTON CMN 
(Construction)
Start: July 25, 7:00 a.m. End: October 31, 5:00 p.m.
 
COLLEGE DR WB SPEED REDUCTION FROM MCORMOND DR TO MCKERCHER DR
(Construction)
Start: July 5, 9:00 a.m. End: November 30, 5:00 p.m.
 
AVE H S INTERSECTION CLOSED AT 11TH ST W
(Construction)
Start: March 11, 7:00 a.m. End: August 31, 5:00 p.m.
 
All restrictions will be lifted as indicated, weather permitting and barring any unforeseen circumstances.
Slow down, pay attention and respect work zones. Watch for pedestrians and work crews, and for everyone’s safety, please obey all detours, signs and barriers.