NEW

MCORMOND DR INTERSECTION CLOSED AT BRIGHTON COMMON
(Construction)
 Start: July 25, 7:00 a.m. End: October 31, 5:00 p.m.

CIRCLE DR E NB & SB MEDIAN LANES CLOSED AT COLLEGE DR
(Streetlight repairs)
Start: July 25, 9:30 a.m. End: July 25, 10:30 a.m.
 
ONGOING
 
8TH ST E EB CURB LANE CLOSED FROM GROSVENOR AVE TO CAMPBELL AVE
(Sanitary sewer lining)
Start: July 24, 9:00 a.m. End: July 25, 3:00 p.m.
 
VICTORIA AVE ALL DIRECTIONS CLOSED AT ASH ST E
(Open cut water main rehab)
Start: May 22, 10:00 a.m. End: July 29, 5:00 p.m.
 
VICTORIA AVE INTERSECTION CLOSED AT ADELAIDE ST E
(Open cut water main rehab)
Start: July 11, 9:00 a.m. End: July 29, 5:00 p.m.
 
CONFEDERATION DR SB CURB LANE CLOSED FROM LAURIER DR TO 22ND ST W
(Concrete repair)
Start: July 15, 9:00 a.m. End: July 29, 5:00 p.m.

BOYCHUK DR NO RESTRICTIONS AT HIGHWAY 16
(Interchange Construction)
NB to WB & EB to SB will continue to use temp intersection. 2-way traffic on NB side of structure.
Start: September 30, 12:00 a.m. End: July 31, 4:00 p.m.
 
MCORMOND DR SINGLE LANE NB & SB FROM KERR RD TO HIGHWAY 5
(Interchange Construction)
Start: November 14, 8:00 a.m. End: July 31, 5:00 p.m.
 
PRESTON AVE S NB PARKING LANE CLOSED FROM LOUISE ST TO ARMISTICE WAY
(Concrete replacement)
Start: July 23, 7:00 a.m. End: August 1, 5:00 p.m.
 
LENORE DR EB CURB & CENTRE LANE CLOSED FROM WARMAN RD TO CREE CRES
(Concrete replacement)
Start: July 17, 9:00 a.m. End: August 1, 5:00 p.m.
 
WANUSKEWIN RD SB LANES CLOSED AT 71ST ST E
(Road construction)
2-way traffic maintained in NB lanes
Start: May 27, 9:00 a.m. End: August 6, 5:00 p.m.
 
CUMBERLAND AVE S INTERSECTION CLOSED AT 14TH ST E
(Water main rehabilitation)
Start: July 8, 7:00 a.m. End: August 9, 5:00 p.m.
 
7TH AVE N ROAD CLOSED FROM QUEEN ST TO WARBURTON ST
(Water main replacement)
Start: July 2, 7:00 a.m. End: September 2, 5:00 p.m.
 
SID BUCKWOLD BRIDGE NB & SB LANES RESTRICTED
(Bridge upgrades)
Lanes restricted in both directions; NB lanes zipper merge near 8th St. SB single lane starting at 20th St.
Start: April 14, 8:30 a.m. End: October 31, 5:00 p.m.

COLLEGE DR WB SPEED REDUCTION FROM MCORMOND DR TO MCKERCHER DR
(Construction)
Start: July 5, 9:00 a.m. End: November 30, 5:00 p.m.
 
AVE H S INTERSECTION CLOSED AT 11TH ST W
(Construction)
Start: March 11, 7:00 a.m. End: August 31, 5:00 p.m.
 
All restrictions will be lifted as indicated, weather permitting and barring any unforeseen circumstances.