You are here

Daily Road Report, May 28, 2019

For immediate release: May 27, 2019 - 3:00pm
TC19-431

*This report includes road restrictions on Priority 1 (high traffic, high speed) streets only.
 
NEW
 
RUTH ST E WB LANES CLOSED FROM EASTLAKE AVE TO NORMAN CRES
(Sewer lining)
Start: May 28, 7:00 a.m. End: May 28, 4:00 p.m.
 
1ST AVE N SB LANES CLOSED FROM 2ND AVE N TO PRINCESS ST
(Sewer lining)
Start: May 28, 7:00 a.m. End: May 28, 5:00 p.m.
 
CENTRAL AVE NB & SB MEDIAN LANES CLOSED AT 115TH ST
(Sewer lining)
Start: May 28, 9:00 a.m. End: May 28, 5:00 p.m.
 
CIRCLE DR W NB CURB LANE CLOSED FROM LAURIER DR TO 33RD ST W
(Street light replacement)
Start: May 28, 9:30 a.m. End: May 28, 11:30 a.m.

OVERNIGHT

EXPRESSWAYS ROTATING LANE RESTRICTIONS
(Street Sweeping)
Start: May 15, 8:00 p.m. End: June 12, 6:00 a.m.
 
ONGOING
 
HIGHWAY 16 EB MEDIAN LANE CLOSED AT BOYCHUK DR
(Waste removal from median)
Start: May 26, 7:00 a.m. End: May 28, 3:00 p.m.
 
VICTORIA AVE INTERSECTION CLOSED AT ASH ST E
(Open cut water main rehab)
Start: May 22, 10:00 a.m. End: June 5, 5:00 p.m.

WANUSKEWIN RD SB LANES CLOSED AT 71ST ST E
(Road construction)
2-way traffic maintained in NB lanes
Start: May 27, 9:00 a.m. End: July 23, 5:00 p.m.

MCORMOND DR SB LANES REDUCED TO SINGLE LANE AT CROSSOVER; SB TRAFFIC USE OVERPASS TO ACCESS COLLEGE
(Interchange work)
Start: April 3, 1:00 p.m. End: July 31 5:00 p.m.

BOYCHUK DR 2-WAY TRAFFIC ON NORTH SIDE OF INTERCHANGE AT HIGHWAY 16; NB LANE TEMP INTERSECTION
(Interchange construction)
Start: September 30, 2018 12:00 a.m. End: July 31, 2019, 5:00 p.m.

MCORMOND DR NB & SB SINGLE LANE FROM KERR RD TO HIGHWAY 5
(Interchange Construction)
Start: November 14, 8:00 a.m. End: July 31, 5:00 p.m.

SID BUCKWOLD BRIDGE NB & SB LANES RESTRICTED
(Bridge upgrades)
Lanes restricted in both directions; NB lanes zipper merge near 8th St: SB single lane starting at 20th St.
Start: April 14, 8:30 a.m. End: October 31, 5:00 p.m.

AVE H S INTERSECTION CLOSED AT 11TH ST W
(Construction)
Start: March 11, 7:00 a.m. End: August 31, 5:00 p.m.
 
All restrictions will be lifted as indicated, weather permitting and barring any unforeseen circumstances.
Slow down, pay attention and respect work zones. Watch for pedestrians and work crews, and for everyone’s safety, please obey all detours, signs and barriers.